Overhead Line
Substation
Underground Electric Construction
Line Clearance Tree Trimming
Plumbing
Process Piping
Fire Protection
Custom Metals Fabrication
HVAC
Wind Energy
Environmental Sensitivity
Solar Hot-Water Heating
Water Reclamation
LEED Certification
Geothermal
Project Management
Safety
Fleet Services
Virtual Design and Construction
General Heating and Air Conditioning
Large Project Capabilities
Emergency Response
Safety
History
Community Outreach
Team Leaders
News and Announcements
OnSite Newsletter
Operations
Corporate
Project Inquiry
Overhead Line
Substation
Underground Electric Construction
Line Clearance Tree Trimming
Plumbing
Process Piping
Fire Protection
Custom Metals Fabrication
Marketing / Website Feedback
Friday, May 18, 2012 Print Share Home Site Map Employee E-Mail / Logon
Get the Flash Player to see this movie.

Industries We Serve

Overhead Line

Project Profiles Archive

2008 Cedar Rapids, IA Flood

2008 Cedar Rapids, IA Flood


Owner: Alliant Energy
Completed: June 2008
Location: Cedar Rapids, Iowa
Description: Flood event lasted from June 8 to July 1. With storms and historic flooding in the roughly 1700 city blocks in the Cedar Rapids area, 32,000 Alliant Energy customers were without power as the Cedar River crested over 32 feet. Alliant Energy’s emergency operations center was evacuated. A temporary substation was constructed to provide power to customers.

View Project Profile


161 kV Q2 Transmission Line

161 kV Q2 Transmission Line


Owner: Dairyland Power
Completed: October 2008
Location: Wisconsin
Description: Rebuilt a seven structure segment of 161 kV line in the lower Wisconsin River Bottom by using ice roads, matting, and helicopters to reach the difficult sections.

View Project Profile


20 Mile 345 kV Storm Damage Transmission Line Rebuild

20 Mile 345 kV Storm Damage Transmission Line Rebuild


Owner: Alliant Energy
Completed: July 2007
Location: Iowa
Description: Redesigned and restored a 20 mile stretch of 345 kV transmission line from Alliant Energy's Ottumwa Generation Station to Montezuma.

View Project Profile


230 kV Peetz, Colorado Wind Farm Transmission Line

230 kV Peetz, Colorado Wind Farm Transmission Line


Owner: Florida Power & Light
General Contractor: RMT, Inc.
Completed: July 2007
Location: Colorado
Description: 78 Miles of 230 kV single circuit two bundle 795 ACSR transmission line installed during blizzard conditions and in soft, sandy Colorado soil conditions.

View Project Profile


161 kV Transmission Line

161 kV Q11 Transmission Line


Owner: WE Energies
Completed: January 2007
Location: Wisconsin
Description: Reconstruction of a 17 mile section of the Q11 161 kV transmission line running through the bluffs along the Mississippi River between Genoa, WI and La Crosse, WI.

View Project Profile


345 kV Arrowhead-Weston Transmission Line

345 kV Arrowhead-Weston Transmission Line


Owner: American Transmission Company
Completed: December 2006
Location: Wisconsin
Description: 220.2 Miles of 345 kV transmission line installed primarily along existing railroad, gas pipe, highway, and transmission right-of-ways.

View Project Profile


City of St. Louis Storm Wind Storm Restoration

City of St. Louis Storm Wind Storm Restoration


Owner: AmerenUE
Completed: 2006
Location: Missouri
Description: Half million customers without power – the worst in Ameren’s 100-year history. The storm caused extensive tree damage, broken poles, and downed wires, in addition to the loss of more than 400 distribution feeder circuits.

View Project Profile


230 kV Flatrock Wind Farm Transmission Line

230 kV Flatrock Wind Farm Transmission Line


Owner: PPM Energy
General Contractor: RMT, Inc
Completed: November 2005
Location: Syracuse, NY
Description: 11 Miles of 230 kV transmission line and 4 miles of 34 kV double circuit T-2 556 MCM distribution line were installed approximately 75 miles northeast of Syracuse, NY.

View Project Profile


Kansas City Ice Storm Restoration

Kansas City Ice Storm Restoration


Owner: Kansas City Power & Light
Completed: February 2002
Location: Kansas
Description: Distribution

View Project Profile